Construction Update

From New Jersey American Water

April 2010

Dear Resident,

As part of our ongoing infrastructure maintenance program in conjunction with the NJDOT Rt. 52 road reconstruction, New Jersey American Water will be replacing the water mains in your neighborhood.

Phase I of the project: Starting Monday, April 5, 2010 and continuing until approximately April 16, 2010 our contractor, J.F. Kiely will begin replacing the water main on Bay Ave. between 9th and Revere Pl.

Phase II of the project: Starting Monday, April 12, 2010 and continuing until approximately April 16, 2010 our contractor will be replacing the water main along 9th St. between Asbury and West Aves. Also starting on Monday April 19, 2010 and continuing until approximately April 29, 2010, Phase II of the project will include the water main replacement along 9th St. between West and Bay Aves.

Phase III of the project: Starting May 3, 2010 and continuing until May 13, 2010 our contractor will be replacing the water main that crosses 9th St. from Haven to Aldrich Rd.

Construction for all of these phases will be performed weekdays between 7:00 a.m. and 6:00 p.m.

During construction, a portion of the affected roadways will be closed as construction proceeds, in accordance with the Ocean City Police Department's approved detour plan. Access will be maintained for residents and businesses at all times.

Because this project requires us to keep the ground dry at the construction site, we may be running a dewatering pump 24-hours a day. Please be assured that we will make every effort to keep noise from this procedure to a minimum.

Thank you for your patience and understanding while we complete this project.

If you have any questions, please contact our Construction Department at 609-677-4634 or our Customer Service Department at 1-800-NJ-AM-WTR (1-800-652-6987).

Sincerely,

New Jersey American Water